Kashigaon, Gorkha
SHREE MANJUSHREE SECONDARY SCHOOL
Reconstruction of the school
Place
Kashigaon,
Ward-6,
Dharche Rural Municipality,
District Gorkha
Who
Implementation: Chay Ya Nepal,
Advisory Council: Dharche Rural Municipality
Partners
Earth C-Air Switzerland,
Chay Ya Switzerland
When
2018 - 2018
For
400 students
Status
Completed and in operation
Project
The school rebuilding and rehabilitation project was carried out through the financial support of Earth C-Air, Chay Ya Switzerland and implementation work at community level was carried out by Chay Ya Nepal.
In consultation with the stakeholders of the school, the construction management committee was chosen, of which “School Management Committee” was unanimously given authority for the construction process. The meeting was followed by the coaching sessions on school design teachings to the contractor of the school: foundation depth, stonewall construction alignment, wall bands. Rod tie-ups and etc., along with measuring the land area for the school construction was concluded during the school stakeholder meeting.
The foundation laying program was organized on 27 April 2018.
The school building was constructed on stone cement mortar, comprising 6 classrooms and providing education facilities to 400 students.
Sustainability Claimer
Due to the special focus on sustainability, the teachers’ salaries as well as the teaching material at the schools we support are normally paid by the government.
Under special circumstances, such as in very remote schools or in the case of marginalised ethnic groups, these costs are covered by Chay Ya for one year.